3,200,000 t/y Delayed Coking Unit of ZPC 40,000,000 t/y Refinery Integrated Project Phase 1
Date Issued:2020-09-09 Page View:

Project name | 3,200,000 t/y Delayed Coking Unit of ZPC 40,000,000 t/y Refinery Integrated Project Phase 1 |
Owner | Zhejiang Petroleum & Chemical Co., Ltd. |
Country | Ningbo, China |
Work scope | Process equipment, piping, E & I, telecommunications, HVAC, fire-fighting, supply of water and drainage, steel structure, painting and insulation. |
Duration | 2017.08-2018.08 |
Description | The project is located in Zhoushan Green Petrochemical Base of Zhejiang Province and is a supporting unit for ZPC Refinery Integrated Project Phase 1 - a major project of China (Zhejiang) Pilot Free Trade Zone. The project set a record for the shortest process of putting into production of similar units in China. |