Recently, the hoisting of four LNG unloading arms at the LNG receiving terminal jetty of the 2×450 MW Gas-Fired Combined Cycle Power Plant Project in Koh Kong Province, Cambodia, undertaken by the Seventh Branch of China National Chemical Engineering Sixth Construction Co., Ltd. (CC6), was successfully completed. This achievement marks the first offshore hoisting operation of LNG unloading arms in Cambodia.
The hoisting operation involved four LNG unloading arms, each weighing 39.5 tonnes. The project team deployed a 2,590-tonne-class barge, together with a 260-tonne crawler crane and a 130-tonne crawler crane, to carry out the coordinated lifting operations. The hoisting of all four unloading arms was successfully completed over a period of three days, laying a solid foundation for subsequent jetty pipeline construction, system commissioning, and project startup. Upon completion and startup, the power plant is expected to reliably supply 20% to 25% of Cambodia's electricity demand, effectively alleviating local power shortages, further optimizing the regional energy supply structure, and supporting the upgrading of Cambodia's energy infrastructure.
This three-day offshore hoisting operation was not only a test of the team's capabilities in organizing and executing heavy equipment installation, but also a vivid demonstration of its ability to translate technical plans into practical construction results and ensure project delivery through refined management. Faced with the challenges of offshore hoisting, the project team adhered to a systematic approach featuring planning in advance, engineering calculations, and strict process control. Taking into account the structural characteristics of the equipment, lifting point arrangements, center-of-gravity positions, available working space, and crane performance, the team developed a dedicated hoisting plan for the LNG unloading arms and completed the required expert review and technical assessment procedures. The team also systematically identified the technical requirements, potential risks, and control measures for each stage of the hoisting operation.
The successful hoisting of all four LNG unloading arms represents a significant milestone in the installation of jetty equipment and a major achievement for the CC6 project team. It also provides valuable practical experience in offshore transportation of heavy equipment, floating platform operations, tandem lifting with two cranes, and risk management under complex working conditions. The experience gained will serve as a valuable reference for CC6 in undertaking similar offshore heavy equipment lifting operations and related projects in the future.